Reimbursement of costs for subsidizing citizens for inverter air conditioners in the Municipality of Tetovo

Monitoring matrix

No.Monitoring criterionStatusDescription & commentsSource
I. Implementation of the monitored measure
1.1Budget funds allocated in the municipality's 2026 budget for implementing the measure No

The Municipality has not allocated any funds in its 2026 budget for the implementation of this measure.

Municipality of Tetovo: Response to a Request for Access to Public Information (email).

1.2Public procurements planned and/or carried out in relation to the measure No

The Municipality of Tetovo is not currently conducting any public procurement procedures, nor does it have any active calls for subsidies for inverter air conditioners for households.

ESJN (Electronic Public Procurement System): https://www.e-nabavki.gov.mk/PublicAccess/Home.aspx

1.3The necessary preconditions for carrying out activities related to the measure are in place (e.g. permits, preparatory activities, staff, etc.) No

No activities have been undertaken to establish the necessary preconditions for implementing the measure.

Municipality of Tetovo: Response to a Request for Access to Public Information (email).

1.4Concrete activities related to the measure are being implemented No

The Municipality has not planned to implement this measure in 2026.

Municipality of Tetovo: Response to a Request for Access to Public Information (email).

II. Transparency and accountability of the municipality/institution
2.1The municipality (i.e. the responsible institution) regularly shares information about the measure on its website and social media No

During the reporting period, no news or information was published on the Municipality’s official website or social media channels.

During the reporting period, no news or information was published on the Municipality’s official website or social media channels.

2.2The municipality (i.e. the competent institution) responds to requests for public information submitted about the specific measure Yes

Of the two requests for access to public information submitted to the Municipality of Tetovo, the Municipality responded to one. The second request, submitted on 18 September 2026, is still within the statutory response period, which expires on 17 October 2026.

The team of the “For Tetovo” organisation.

2.3The municipality (i.e. the responsible institution) shares information about the measure at the request of stakeholders through meetings, interviews, gatherings, etc. No

No information is available to indicate that any meetings, consultations, interviews, or other activities were held during the reporting period at which information about the monitored measure was shared.

Official website and Facebook page of the Municipality of Tetovo.

III. Citizen participation in decision-making
3.1Citizens are involved in decisions related to the implementation of the measure No

No formal consultations or meetings with citizens were held regarding the implementation of the monitored measure, and no information is available on whether citizens were consulted through other channels.

Official website and Facebook page of the Municipality of Tetovo.

3.2Citizens have initiated participation in decisions related to the monitored measure No

No information is available to indicate that, during the reporting period, citizens initiated participation in decisions related to the monitored measure through requests, petitions, civic initiatives, or other forms of public participation.

The team of the “For Tetovo” organisation.

Citizens were involved in the implementation of the specific measure through:
3.3.1Public assemblies, debates and forums No

No public gatherings, debates, or forums were organised during the reporting period.

The team of the “For Tetovo” organisation.

3.3.2Possibility of electronic participation via mobile apps, website, online forms, etc. No

During the reporting period, no opportunities were identified for citizens to participate electronically (via the website, electronic forms, mobile applications, or other digital tools) in relation to the monitored measure. Consequently, no electronic consultations or other forms of electronic citizen participation concerning this measure were conducted.

The team of the “For Tetovo” organisation.

3.3.3Municipality open days No

No information is available to indicate that an open day was held to discuss the monitored measure.

The team of the “For Tetovo” organisation.

Stagnation
Municipality Tetovo
Organisation Association for Civic Development “For Tetovo”
Financial indicator (municipality) Open