Citizens nearby - multi-store garage in Ohrid

This initiative will monitor the implementation of the electoral promise related to the construction of a multi-store garage in municipality of Ohrid and the level of citizen participation and inclusion in the process of urban planning. This will enable the public to get better insight in the current developments, the dynamics and the remaining activities of the local self-government regarding this issue. Community mobilization activities will include: meeting with relevant representatives of the local self-government and requesting the feasibility study for construction of the garage to be shared; public outreach and presentation of the findings on the local media and similar.

The subject matter of the local monitoring is the construction of a multi-store garage in Ohrid.

Implementer
Association for multicultural integration - Inclusion Ohrid
Location
Ohrid
Budget
300000 denars
Status
Active

MONITORING MATRIX

  • I. Status of the monitored item

      Monitoring criteria Status Brief description and comments Source of information
      1 Implementation
      1.1 A decision has been reached to start the implementation of the monitored item After the meeting with the Mayor of the Municipality of Ohrid, the meeting with councilors from the Council of the Municip. of Ohrid and with the Head of the Urban Planning Sector, no decision has been reached for the construction of the multi-store garage Mayor and Head of the Urban Planning Sector
      1.2 A procurement process is being/has been carried out related to the monitored item Yes Yes, with the project and planning documentation process, i.e. the preparatory activities for the construction of the multi-store garage, are declared in the Municipality of Ohrid's development program, category: "Arrangement of the construction land'' In the Municipality of Ohrid's development program, category: "Arrangement of the construction land" during 2022-2024, department B: "Asphalting and reconstruction of streets and access roads" serial number 3. " Development of a project as well as technical documents for the construction of the multi-store garage", for which are envisioned 4 300 000, 00 denars. ("Official Gazette of the Municipality of Ohrid " no. 17 of 12/30/2021, p.17).
      1.3 Informative meetings and gatherings with stakeholders have been held Yes Yes. So far, several meetings are held with the mobilizers and the project team. Meeting with the Mayor of the Ohrid Municipality, the Head of the Urban Planning Sector, the Councillors of the Ohrid Municipality, and the Association Archrid - Ohrid. On December 23, 2022, mobilizers and the project team had a press conference in front of the local media. On December 26, 2022, the mobilizer met the Mayor of the Municipality of Ohrid, Dr Kiril Pecakov. On January 24, 2023, a meeting was held with the Head of Urban Planning, and the Feasibility Study was officially submitted. On January 24, 2023, the community mobilizers and the project team held an informative meeting with the Ohrid municipality council members. On January 25, 2023, the community mobilizers and the project team held an informative meeting with other members of the Ohrid municipality council. https://powerinfo.mk/%d0%b7%d0%b0%d0%bf%d0%be%d1%87%d0%bd%d0%b0-%d0%b8%d0%bc%d0%bf%d0%bb%d0%b5%d0%bc%d0%b5%d0%bd%d1%82%d0%b0%d1%86%d0%b8%d1%98%d0%b0%d1%82%d0%b0-%d0%bd%d0%b0-%d0%bf%d1%80%d0%be%d0%b5%d0%ba%d1%82%d0%be/ https://www.facebook.com/Inclusionohrid/posts/pfbid0kwcyXuxPU4SVmYna2fcVCWeAUxa9NeNjDruxShPxzzvx3cPQrKC2o4Yq3GK3Qvxdl https://www.facebook.com/126831140720204/posts/pfbid09Yaakj45CwAf7P5ELzzGduVjcrrBxjWbE8CAGHjWAXh8T5kQ4nUz85XqJGfDeeEql/?mibextid=Nif5oz https://www.facebook.com/126831140720204/posts/pfbid0iLFny1tkkHwdGQMnFgPejvkKjG65U2BbdeMDmnD7px1UFrrPZrsfcTiyr9nCeVugl/?mibextid=Nif5oz https://www.facebook.com/126831140720204/posts/pfbid0MJpGa2XGa4jCFE8cgA92pSzu7DSVzaN3cD6FwwDzs8QeSc3uDNGtxWgXPURRsWjfl/?mibextid=Nif5oz
      1.4 An implementation plan has been prepared for implementation of the monitored item No information /
      1.5 Necessary prerequisites to start with the implementation have been provided (e.g. permits, preparatory activities, staff, etc.) The Mayor of the Municip. of Ohrid answers questions from the media regarding the received conservation consent for a multi-store garage/on 13.02.2022. At the meeting with the mobilizer, he pointed out expected construction and UNESCO Commission approval. Interview with the Mayor of the Municipality of Ohrid (https://ohrid24.mk/?p=24194&fbclid=IwAR1vQxb__J-aV32lpfPuZyo6yz0sqwJdfpH8rzPkmRlrjEeMuB0PpsXlIuo) Meeting with the Mayor and the Head of the Urban Planning Sector.
      1.6 The municipality is implementing specific activities from the implementation plan No visible specific activities from the plan have begun. Media text https://tvm.mk/news/ohrid/katnata-garaza-zaglavena-vo-birokratska-lavirint/
      1.7 Initial results from implementation of the monitored item are visible There are no initial visible results from the project implementation Media text https://tvm.mk/news/ohrid/katnata-garaza-zaglavena-vo-birokratska-lavirint/
      2 Stagnation
      2.1 Lack of funds in the municipal budget N/A No information. In a conversation with the Mayor of the Municipality of Ohrid, he points out that it's very likely to have a public call for the multi-store garage construction and to be constructed with deferred payment. Conversation with the Mayor of Ohrid Municipality, Dr Kiril Pecakov.
      2.2 Lack of one/some of the basic prerequisites Yes The administrative procedures are in the final stage, but the project is stagnant. Information from the conversation with the Mayor and the Head of the Urban Planning Sector.
      2.3 The implementation of the monitored item is no longer a priority The Mayor points out that the multi-store garage stands out through meetings with citizens as the top 3 priority solutions for the Municipality of Ohrid, the same is recognized by the Councilors of the Municipality and the Head of Urban Planning. The VMRO-DPMNE program for 2021 Local Elections (https://vmro-dpmne.org.mk/%d0%bb%d0%be%d0%ba%d0%b0%d0%bb%d0%bd%d0%b0-%d1%81%d0%b0%d0%bc%d0%be%d1%83%d0%bf%d1%80%d0%b0%d0%b2%d0%b0?fbclid=IwAR26NRVyn3b6Dcw03fs1ENwKibRSg7lL7EGNnIXzEi0toNcd_egXMWSyd-A) The mayor points out that the multi-store garage stands out through meetings with citizens as the top 3 priority solutions for the municipality of Ohrid, the councillors of the council of the Municipality of Ohrid, who are in opposition, as well as the Head of the Urban Planning Sector, also point out the same through a conversation with the implementers of the initiative.
      2.4 Halted due to an inspection, investigation, etc. There is no information regarding any held investigations. /
      2.5 The reasons for the stagnation of the implementation of the activity are unknown Yes There is no public information available on the reasoning behind the stagnation, although it can be concluded from the discussions that the obstacles are administrative.
  • II. Transparency and accountability of the municipality related to the monitored item

      Monitoring criteria Status Brief description and comments Source of information
      1 Information about the status of the monitored item is available on the municipality's website and social network There is no information available on the municipality's website regarding the status of the project. Website of the Ohrid Municipality (https://ohrid.gov.mk/)
      2 Information about the status of the project is obtained through a Request for Access to Public InformationInformation about the status of the monitored item is obtained through a Request for Access to Public Information Yes The community mobilizers and project team have submitted an official request to the Municipality of Ohrid, to obtain the feasibility study for the multi-store garage and a conversation request with Head of Urban Planning. Under archive number 122/2 2022, an official request for obtaining a feasibility study is submitted. At the same time under No. 03-16243/1 dated 22.11.2022 were delivered a CD with an electronic version of the Feasibility Study on the justification of the construction of a multi-store garage in Ohrid with Tax. No. 03-186/19 dated March 2019, prepared by the Institute for Testing Materials and Development of New Technologies "Skopje" AD Skopje.
      3 Information about the status of the monitored item is shared with stakeholders by municipal officials (via e.g. interviews, focus group discussions, meeting requests etc.) Yes Yes. The Mayor of the Municipality of Ohrid, Dr Kiril Pecakov, had a meeting with the local mobilizer. Meetings were also held with Councilors from the Ohrid Municipality Council, the Head of the Urban Planning Department, the Association Archrid Ohrid . Local mobilizers from the Inclusion Organization.
      4 There is practice of informal information sharing by the municipality with affected citizens (e.g. via informal discussions etc.) Yes Yes. The mayor is constantly with the citizens, and there is an open discussion of the municipality's problems. Citizens, NGOs, Stakeholders.
  • III. Citizen participation in decision-making related to the monitored item

      Monitoring criteria Status Brief description and comments Source of information
      1 The municipality has involved the citizens in decision-making related to the monitored item The municipality has not involved the citizens in the decision-making process concerning the monitored issue, and the Municipality of Ohrid has an involvement mechanism for the citizens to partake in decisions, for example, opening day, public sessions etc https://powerinfo.mk/%d0%be%d1%82%d0%b2%d0%be%d1%80%d0%b5%d0%bd%d0%b8-%d0%b4%d0%b5%d0%bd%d0%be%d0%b2%d0%b8-%d0%bd%d0%b0-%d0%be%d0%bf%d1%88%d1%82%d0%b8%d0%bd%d0%b0-%d0%be%d1%85%d1%80%d0%b8%d0%b4-%d0%b7%d0%b0-%d0%bf%d1%80/
      2 Citizens have filed an initiative for participation in decision-making related to the monitored item The citizens did not submit an initiative to participate in the decisions related to the monitored issue, but it’s often discussed at tribunes and meetings with citizens Mayor of Ohrid, Citizens
      3 Citizens participate in the implementation of the monitored item with their input and resources N/A The monitored issue represents a serious capital investment of the municipality, for which there are certain financial sources, and the citizens have not contributed via their resources and participation. Resources of project financing https://ohrid.gov.mk/wp-content/uploads/2017/08/Sluzben_glasnik_2021_17.pdf)
      4 Mechanisms utilized by the municipality to ensure citizen participation, specifically as related to the monitored item:
      4.1 Public gatherings, debates and forums There is no information about held public events. Association "Inclusion" - Ohrid, as part of the initiative activities, has organized a one-day public debate titled "Multi-Store garage - a new opportunity for Ohrid". Organizing a one-day public debate titled "Multi-story garage - a new opportunity for Ohrid" with interested citizens, experts and competent authorities - as part of the activities of the initiative Citizens nearby - a multi-story garage in Ohrid.
      4.2 Possibility for e-participation via mobile apps, website(s), electronic templates, etc. Yes The section - report a problem on the municipal website of Ohrid (https://ohrid.gov.mk/%d0%ba%d0%be%d0%bd%d1%82%d0%b0%d0%ba%d1%82/)
      4.3 Open days of the municipality Yes The municipality has a system regarding the municipality's open days, however there is no further information on this issue. Media coverage on the municipality's open days (https://www.ohridnews.com/otvoreni-denovi-na-opshtina-ohrid-za-predlozheniot-bu-et-za-2023-godina/)
      4.4 Citizen initiatives There is no information about other civil initiatives filed on this matter. The citizens did not submit an initiative to participate in the decisions related to the monitored issue, but it’s often discussed at tribunes and meetings with citizens. Website of the municipality (https://ohrid.gov.mk/) Mayor of Ohrid